The government unlocks 57 construction sites, for an investment of 83 billion

by time news

Time.news – Twenty-nine extraordinary commissioners appointed for 57 works public blocked due to delays in the design and executive phases and the complexity of administrative procedures. Works that the government has already financed for 33 of the 83 billion needed to complete them, which will lead to the creation of 100,000 jobs by 2027.

These are the numbers and the forecasts of the government that today with the appointment of commissioners has given the green light to the unblocking of the construction sites. The executive expects an important impact from the works also on the employment side, the effects of which will begin to be seen next year. Prime Minister Mario Draghi he has no doubts: “We are sure that the construction sites will be opened on the dates indicated. The certainty comes from the fact that the procedures have been completed or will be completed within the indicated deadlines”.

A second decree will arrive by June with further works to be released, but from a first calculation of the Minister of Infrastructure and Sustainable Mobility, Enrico Giovannini, the impact on employment should be seen soon. “Not immediately”, the minister specified, “because this year it will mainly concern architects and engineers. But from next year an impact of 20,000 work units is calculated, which will gradually increase: 37,000 in 2023, up to 100,000 between 2026 and 2027 ”.

A note from Mims listed the works that will begin to come to life in the coming months: it is 16 railway infrastructures, 14 road, 12 barracks for public safety, 11 water works, 3 port infrastructures and an underground, for a total value of 82.7 billion euro (21.6 billion in the North, 24.8 billion in the Center and 36.3 billion in the South) financed, under current legislation, for approximately 33 billion euro.

The funding will be complemented with additional national and European resources, including the Next Generation Eu, but additional resources may come with the National Recovery and Resilience Plan. “I asked all the commissioners about the quarterly time schedules,” Giovannini specified.

“I will meet them all next week – added the minister – assuring the fact that the ministry will monitor their work on a quarterly basis, in order to intervene promptly to help them solve the problems “. Then a clarification:” Unfortunately, few works of these commissariats will immediately start the construction sites, because many works are blocked in the design or pre-design phase in some cases “.

As for the commissioners nominated, in the note released by Mims, are described as “highly professional technical-administrative figures”, who will be “immediately operational“And” choices to ensure the best dialogue with the contracting stations of Anas and RFI and with the various public administrations involved “. Only in one case, as foreseen by a Cipe resolution, was the president of the Sicilian Region appointed as extraordinary commissioner.

.