(31/07/2023)
The contract includes the drafting of the project and the execution of the works, the tests and the commissioning of the security installations in the ten kilometers of the line between the two municipalities, currently in disuse that is going to be recovered for the Cercanas service.
The contract, awarded to Enclavamientos y Signalización Ferroviaria, Enyseincludes the control, command and signaling facilities, energy and civil works and new systems and signals and has an execution period of 32 months, eight for drafting the project and twenty-four for works and tests.
recovery
Adif has begun work to recover the section without service that starts from Colmenar Viejo where line C-4b ends and reaches Soto del Real, in which it will invest 21.8 million euros, to which 9.7 million are added. more in supplies, assistance, projects, etc.