Federal government warns that in the future it will not finance all solar energy projects

by time news

2023-11-08 05:48:58

Although the federal Department of Energy (DOE) has held talks with the 10 private developers of the first round of large-scale solar projects, with a view to offering them financing for the construction of the works, the head of the Loan Program Office (LPO)Jigar Shah, cautioned that the expectation is that, during future tranches, proponents will turn to private capital.

“Our goal is to build trust between the different actors, so that we attract more capital from the private sector to Puerto Rico. We see ourselves as a bridge to the future; “The goal is not to be the main source of financing forever,” Shah said.

The federal official explained that the Energy Infrastructure Reinvestment Program – one of the initiatives under the LPO – allows the DOE to grant loans to projects that aim to replace fossil energy sources with renewable alternatives.

Under the first tranche or “tranche” of acquisition in accordance with the Integrated Resource Plan (PIR), The Bureau of Energy (NEPR) gave way to 11 solar energy initiatives in the hands of 10 proponents, since Clean Flexible Energy – a subsidiary of AES – owns two projects. All these investments are accompanied by five battery energy storage proposals.

LPO financing can cover 80% of eligible costs, Shah said, at an interest rate equal to the rates set by the US Treasury Department plus 0.375%.

“The loans have to be repaid, so there is no forgiveness, but we are willing to take risks that, perhaps, a private bank would not take,” stated the director of the LPO.

Obstacles with the first section

The 11 photovoltaic and five battery projects must have an interconnection agreement with LUMA Energy on or before November 30, but, as of last week, only four proponents had signed the document with the consortium.

The president of the Governing Board of the Electric Power Authority (AEE), Francisco Berríos Portela, acknowledged that the increases in costs, compared to initial projections, have complicated the negotiations. The NEPR, in recent months, determined that developers would not assume the differences that would have occurred as a result of factors such as inflation.

“Loans are just that, they are not a magic wand. But I would say that since we do all the due diligence for the loans, we can close the trust gap between the Fiscal Oversight Board (FSB), the NEPR and the developers. There are many parties that do not trust each other,” said the federal official.

Shah could not say whether all the developers of the first “tranche” had applied for a loan with the LPO or how many have been approved, stating that this is confidential information. According to the contractually stipulated dates, all projects must be built and supplying energy to the grid between September and November 2025.

“I can’t say which ones are applying, but we have contacted all 10 (developers) and we are meeting with all of them this week,” he said. In an interview with this newspaper during her visit to Puerto Rico at the beginning of the month, the Secretary of Energy, Jennifer Granholm, stated that “almost all” of the planners had requested a loan with the LPO.

In September, the Board gave way, with certain conditions, to amendments to the power purchase contracts between PREPA and the 10 developers, but pointed out that they implied a 34% increase in costs compared to the original agreements. However, Shah stressed that, despite the amendments, the price will continue to be “competitive” for consumers.

“We believe that, as long as the loan is extended, (the projects will provide) some of the cheapest energy in Puerto Rico,” he said. The “Tranche 1” power purchase contracts extend until 2047.

The NEPR, according to the PIR, must complete six rounds of procurement, as part of the effort to meet the renewable energy portfolio required by law.

#Federal #government #warns #future #finance #solar #energy #projects

You may also like

Leave a Comment