They enabled a double bridge on Bulevar Lourdes, zone 5 of Guatemala Metropolis – 2024-06-17 06:08:18

by times news cr

2024-06-17 06:08:18

The Municipality of Guatemala reported that the development of the double bridge on Lourdes Boulevard has ended and as of June 14, 2024, the visitors within the space, each non-public autos and heavy transport and cargo. The development of this work responds to the earth erosion recorded on twenty seventh road in zone 5, which triggered the whole closure of the six lanes and the restriction of the passage of heavy transport and cargo via the world.

You may be keen on: Climate for the weekend of June 14 to 16, 2024 in Guatemala

They enabled a double bridge on Bulevar Lourdes, zone 5 of Guatemala Metropolis

The street spokesperson of the Municipality of Guatemala, Amilcar Montejoreported that as of Friday, June 14, vehicular passage over the double bridge on Lourdes Boulevard In each instructions it’s enabled. In accordance with experiences, this new infrastructure was carried out with the aim of easing visitors in a vital space of ​​town, benefiting the roughly 70,000 autos that flow into via the world.

The development of the bridge was carried out with the target of bettering visitors situations, particularly contemplating that this part connects the Atlantic port with necessary areas such because the Terminal, the Historic Middle, the Civic Middle and in addition connects with the Campo Marte space. Subsequently, zones 5, 1, 4, 9, 10, 15, 16, 17, 18, 24 and 25 will instantly profit from this new infrastructure. As well as, it was reported that municipal work will proceed within the environment of the work to proceed bettering the street infrastructure within the space.

Double bridge the place heavy and cargo transport can flow into

The work is made up of two bridges, every with two lanes that permit circulation in each instructions. With the passage enabled, heavy and cargo transport can now use this part. The opening of this crossing is a aid for each non-public drivers and industrial transportation, which might now journey via the world.

Work completes on account of sinkhole registered in August 2023

In August 2023, Lourdes Boulevard was affected by a landslide on the top of twenty seventh Avenue, brought on by intense rains that elevated the stream of the wastewater river. This injury worsened in September, resulting in the necessity for detours within the space and building of the construction. The work consisted of 4 phases, which had been labored concurrently to speed up its completion:

  • Part 1: Securing and making ready the land, along with the development of two three-meter-high stream regulators.
  • Degree 2: Development of two short-term lanes to hurry up visitors within the space. As a part of this part, on October 16, 2023, a provisional lane was enabled for folks shifting from zone 5 to zone 16 of Guatemala Metropolis. This part was solely enabled from 6:00 a.m. to 7:00 p.m. and the passage of heavy transport and cargo was not allowed.
  • Part 3: Development of piles for the bridge.
  • Part 4: Development of the double bridge.
Description of the photograph for folks with visible disabilities: picture of the completed work with the data that it’s already enabled. (Credit score: PMT Guatemala Metropolis)