The Southern Gas Company announced today, Monday, the arrival of imported materials for the associated gas investment project in the Nasiriyah and Gharraf fields.
The company’s Deputy Director General, Munther Abdul Wahid, said in a statement received by the (INA): “The imported materials for the completion of condensate pipes andLBG From the associated gas investment project from the Nasiriyah and Gharraf fields, it has reached 15 percent of the project’s completion rate.”
Abdul Wahid added that “these materials will contribute to providing cathodic protection for pipes that extend for long distances and have overlaps with pipes that are in operation to protect them from corrosion, and the company will begin installing them soon,” noting that “there are other imported materials for the pipeline.” LBG To discharge liquefied gas, it was contracted by the Oil Projects Company and the Engineering Equipment Company with one of the international companies, and it will be equipped within a period of 52 weeks from the date of opening the documentary credit.