Comprehensive testing of lines T3 and T4 of the Casablanca Tramway to start soon

by times news cr

2024-04-23 00:06:09

The company specifies, in a press release, that these tests constitute the last phase of the tests and that they will be followed by the dry run in real traffic conditions, recalling that the static tests have already taken place and that the dynamic tests have been started last July.

The same source indicates that the overall tests will take place between 8 a.m. and 10 p.m. at a fairly high frequency of train passage and will make it possible to verify three essential elements to guarantee a future reliable, secure and long-lasting service, namely: the overall functionalities , the operability of the service and the resilience of the transport system as a whole.

Casa Transport emphasizes that on the one hand, it is a question of verifying that all the subsystems fulfill the expected functions. On the other hand, these tests attest that the operating program for future lines is consistent with the operational service of lines T1 and T2.

The project teams also ensure during this phase that the nominal transport service can be restored within an acceptable time frame, in the event of a disruption or malfunction, notes the press release.

The overall test program is spread over 6 periods of one week each, starting February 19 and continuing until March 30.

Casa Transport recalls the importance of respecting the highway code and the exclusivity of the tramway platform, for the safety of project teams and citizens, the press release concludes.

2024-04-23 00:06:09

You may also like

Leave a Comment