IGB operator on reasons for delay in launch of Komotini-DESFA

by times news cr

## 2024-08-09 04:03:52

IGB operator on⁤ reasons for delay ‍in launch of Komotini-DESFA”/>

The commissioning of the​ floating ⁤storage and regasification unit (FSRU) in Alexandroupoli has been ‌delayed, directly impacting ⁤the ⁢planned launch of ⁢the Komotini-DESFA junction point.

ICGB, the operator of⁢ the ⁢Greece-Bulgaria interconnector (IGB), confirmed ​the delay ​in response‍ to a request from Trend.

The commercial operation of the Komotini-DESFA connection point, originally scheduled for 1 July 2024, has been postponed.

“The physical connection of the two systems at the interconnection point has already‍ been completed, although commercial operation has​ not yet commenced. The successful start of commercial operation⁣ of the Alexandroupoli FSRU is crucial ‍for the commissioning of Komotini-DESFA, as it will⁣ enable the physical transfer⁢ of gas through the Greek DESFA transmission⁤ system to IGB. The ongoing ⁣delay​ in commissioning⁤ the facility directly impacts the start of operation of the interconnection point. We look forward ⁣to the ‌start ⁤of the FSRU and will work diligently to ensure ​the earliest ⁢possible launch of Komotini-DESFA operations,” the company stated.

The Komotini-DESFA interconnection point plays ⁤a‌ key role in the IGB, directly ‌connecting the interconnector⁢ system with the‌ Greek national operator’s system.

“This​ line provides access to alternative sources​ of natural gas, ‍including planned and existing liquefied natural gas (LNG) terminals on Greek ⁤territory, thereby enhancing ‌the regional importance of the interconnector. In particular, the strategic synergy between IGB and the FSRU‍ in Alexandroupoli is significant, ‍as the launch ​of the terminal​ is expected to facilitate ​the physical flow of gas from Greece to ‌Bulgaria, further enhancing energy ⁣security and diversifying natural gas supplies to Bulgaria and the wider region,” the company said.

ICGB expressed hope that the ⁢start of ⁣commercial operations ‍of​ the LNG terminal will attract greater ⁢market interest, providing more opportunities for new players ​to book capacity.

The total capacity of IGB is 3 ‍billion ‍cubic meters per year, with ‍about one billion​ cubic meters reserved on ‌a long-term basis under 25-year⁤ contracts for ⁣gas supply from Azerbaijan. The pipeline provides​ more than ​50 percent of Bulgaria’s domestic gas consumption in the winter months‌ and up to 80 percent in ‌the summer season.

ICGB is currently assessing⁣ market⁤ interest in increasing the ‌total capacity to 5 billion ‌cubic meters ⁢per year. This would further strengthen the transit role of Bulgaria and Greece.

You may also like

Leave a Comment