DIG/ NOT yet delivered to users, the footbridge erected at the Léon Mba national high school (LNLM) would have some imperfectionsobserve some engineers.

Notably at the level of the main beams where many cracks would already be visiblethey say.

What could constitute, in the long run, a real danger for users.

Especially since beams are the elements on which all the reinforcement mainly rests.

This situation raises a number of questions. Among other things, according to them, on the quality of the concrete used.

“Did the agents assigned to work control fully and assiduously fulfill their missions?

Did the company in charge of pouring the concrete, namely Jade Beton, comply with the contractual requirements? »they wonder.