New Akanda road: The project will finally be delivered in January 2024

by time news

2023-09-19 10:38:25

DIG/ Scheduled to be delivered, for the first time, in June 2023, the new Libreville airport bypass road leading to the commune of Akanda will ultimately be 6 months late.

The winning company Afcons officially announced in a press release that the road infrastructure will finally be operational in January 2024.

The Indian company mentions difficulties linked in particular to the supply of aggregates and other types of construction materials.

You should know that this project consists of the construction in places of 2×3 lanes and 3×2 lanes over approximately 4.5 km.

It should make it possible to relieve congestion in the north of Libreville to ensure greater fluidity of road traffic.