Latvia faces delayed and inconsistent political decisions that now threaten the Rail Baltica railway project more than technical readiness or construction capacity. Marko Kivila, Chairman of the Management Board of the Baltic joint venture RB Rail, issued a sharp critique of Latvia’s approach as public debate in the country turns once again to whether taxpayers can actually afford the continental link.
Kivila argued that asking whether Latvia can afford the project misses the mark when 4.5 billion euros in European funding has already been allocated to reflect its strategic importance, even as local fiscal pressures and funding challenges persist despite leaders across the Baltic states and Poland reaffirming their commitment to completing the project.
Latvian Ministers Confront Financial Pressures and EU Budget Talks
Latvian Transport Minister Rihards Kozlovskis warned that the country’s current implementation approach is no longer sustainable, explaining on television that Russia’s war in Ukraine and geopolitical developments require serious financial prioritisation while preparing the next state budget.
Currently, all scenarios are on the table.

Rinkēvičs noted that three more European Council meetings are expected before the end of the year, though reaching a final agreement remains uncertain, while negotiations over the next multiannual EU budget will determine the volume of Connecting Europe Facility support and national co-financing available.
Joint Application Seeks Hundreds of Millions From Brussels for 2027 to 2030 Works
RB Rail, coordinating alongside national bodies in Estonia, Latvia, and Lithuania, has lodged a joint application seeking roughly £300M (€357.5M) from the EU Connecting Europe Facility to fund construction and systems work planned between 2027 and 2030, despite political friction in Riga.
Lithuanian rail group LTG noted that Lithuania’s share of this latest request totals 37.3 million euros, which will support high-voltage power network connections at traction substations and land acquisition for the Panevėžys railway junction, with the requested sum split between the CEF Cohesion envelope and the general envelope.

Escalating Budgets and Revised Timelines Across the Baltic States
A cost-benefit analysis conducted in 2017 estimated the entire project at 5.8 billion euros, but today updated estimates place the first phase of the main railway line at 14.3 billion euros across the Baltic states, with Latvia’s share alone expected to reach 5.5 billion euros or up to 6 billion euros after price indexation, and total project costs across the corridor ultimately climbing to 23.8 billion euros.
Coordination and financing hurdles pushed expectations from an initial completion timeline of 2025 to 2030, and in September the Baltic states agreed to push the mainline completion target for the first phase back further to 2034. Kivila cautioned that the actual pace of work in Latvia lags significantly behind neighbouring countries, creating risks where unused EU funding threatens higher future expenses, contract renegotiations, and delayed economic and military mobility returns for the entire region.
Whether final agreement will be reached during the three upcoming European Council meetings before the end of the year remains unknown.