The service in Line 5 The Metro Collective Transportation System could resume until tomorrow after this morning a trailer overturned against a cyclone mesh in the vicinity of the station Oceania.

This was reported by the head of the capital’s government, Marti Batres detailing that the work to remove the unit could last up to 10 hours.

You might be interested in: Sheinbaum asks to protect all Morena candidates in Guanajuato

“It is estimated that they will be between 8 and 10 hours of maneuversof work with cranes and then, operational tests will immediately have to be carried out to see that, in fact, the mobility of the Metro has not been affected,” he explained.

In conference, after supervision tour at the general hospital Ruben Leñero, The capital’s president clarified that there were two victims of this event: the trailer driver who lost his life and his companion who was seriously injured.

“There are two people, there is the driver who, in fact, was taken to the hospital and died and apparently his companion, I think it is his partner,” he said.

You might be interested in: Alex Hernández is eliminated in the first round of the Mexico City Open

Regarding the material damage, he explained that the effects on the Metro Line 5 They were recorded in the trays where all the wiring is deposited, which were practically torn off when the cyclonic mesh was damaged.

“It seems that there is no major damage to the track facilities, in a first inspection, but the corresponding tests will have to be carried out punctually once everything is repaired,” he insisted.


2024-04-05 04:06:12