Scandal in Nowy Sącz! What about the Sandecja stadium? “Mine of oddities” discovered

by time news

The construction of the stadium in Nowy Sącz is not proceeding under normal conditions. Wentlo informs that three times recently it happened that … builders dismantled the building at night. The workers were either tearing down the walls or, in theory, getting rid of things the contractor had done that he shouldn’t have—they just weren’t in the design.

There were so many puzzling events surrounding the construction that the Public Procurement Office became interested in it. As it turned out? Well, during the tender for the construction of the new stadium, the Public Procurement Law Act was violated.

Initially, the plan assumed two stands at the stadium and just over 4,000 seats. seats. However, the plan changed, two more stands were added to it and an annex was signed for the expansion of the stadium.

— Immediately after the tender for the construction of the facility in the “design and build” system was settled, the officials decided to extend the investment by adding additional stands and closing the stadium. In this case, in March last year, the company concluded an annex to the signed contract, and according to UZP, it should launch a separate tender for this project, PAP reported.

You may also like

Leave a Comment