Sedena accelerates work towards delivery deadline

by times news cr

With the aim of opening it before the end of the president’s term Andres Manuel Lopez Obrador (AMLO)currently work is being carried out at full speed on the construction of the Suburban Train to AIFA.

And the work that AMLO himself said would be completed in March 2023 and that its completion has been postponed since then, now the Secretariat of National Defense (Sedena) would be trying to finish it before the September 30 deadline.

So that in the work We work day and night to try to finish the work that connects the Felipe Ángeles International Airport (AIFA) before AMLO leaves.

Suburban Train from Buenavista to AIFA (Especial)

Suburban Train to AIFA: Authorities report that the new branch is approximately 80 percent complete

In front of the various delays that the work has suffered due to Protests by residents of Tultepecwho demanded the payment of compensation, the new branch of the Suburban Train to AIFA presents an approximate progress of the 80 percentas reported by the authorities.

Currently, there is a significant number of workers in the area working on the overpasses that will help connect the 10 de Junio ​​and Teyahualco neighborhoods, which have as their only exit the section where the Suburban train will pass.

Due to the construction of the Dairy-AIFA sectiona section of the Mexiquense Outer Circuit which runs from kilometers 8+500 and 13+540, located between the T-5 Tultitlán toll booth and the exit to the municipality of Tultepec, is temporarily closed in both directions.

It should be noted that The closure of the road will be from 10 p.m. to 6 a.m. to avoid further damage.

Sedena accelerates work towards delivery deadline

AMLO promises to inaugurate the Lechería-AIFA Suburban Train when Delfina Gómez is governor of the State of Mexico (AMLO / Twitter)

AIFA Dairy Section to be completed by 2025

Despite the fact that work was being done at forced marches to complete the new branch of the Suburban to the new airport, the Dairy section to AIFA It would not be finished before the end of AMLO’s six-year term, but rather until the first quarter of 2025.

The Crónica portal reports that workers on the new branch of the Suburban Train confirmed that There is no exact date for the completion of the work.but they assured that will not be in 2024.

In fact, they pointed out that although the authorities have officially reported that the work is 73 percent complete, the reality is that the current progress has not reached 60 percent.

They also indicated that at least half of the stations included in the branch line are experiencing construction delays.

Therefore, the inauguration of the Suburban Train branch to AIFA would be inaugurated by Claudia Sheinbaum.

2024-09-18 23:44:35

You may also like

Leave a Comment