The El Tule vehicular bridge was inaugurated in Asuncion Mita, Jutiapa

by times news cr

2024-08-21 10:48:22

We tell you more about New El Tule vehicular bridge inaugurated in the village of El Tular, in the municipality of Asunción Mita, JutiapaThis structure will benefit thousands of Guatemalans by facilitating transit between local communities and those heading to El Salvador.

Its inauguration takes place almost two years after its construction began in October 2022, following the collapse of the structure caused by heavy rains.

The El Tule vehicular bridge was inaugurated in Asuncion Mita, Jutiapa

On Tuesday, August 20th, inaugurated the El Tule vehicular bridge in the El Tular villagelocated in Asuncion Mita, JutiapaThis new infrastructure represents a significant achievement for the region, as it replaces the old structure that collapsed in June 2022 due to the heavy rains of the winter season. The rainfall caused the Ostúa River to rise, leading to the collapse of the previous bridge and leaving several communities isolated.

He New El Tule bridge This is a project that improves the connection between Guatemala and El Salvador, facilitating transit and commercial activity in the region. This structure directly benefits more than 53,000 inhabitants of communities such as El Tule, Cerro Blanco, Anguiatú, San Benito la Bomba, San Rafael Cerro Blanco, Las Ánimas, Torera and Caserío Lima, who will be able to access products, medical services and education more easily.

Its construction is part of the rehabilitation project of the RD-JUT-44 route, a very important road in the region. The work, which is 100 meters long, was carried out with an approximate investment of 46.7 million quetzales. During the inauguration ceremony, the president of the republic, Bernardo Arévalo; the president of Congress, Nery Ramos; the minister of communications, Félix Alvarado, as well as local authorities were present.

Image description for visually impaired people: View of the inner part of the bridge. (Credit: CIV)

Work started in 2022

Construction of the new El Tule bridge began in October 2022, after the structure collapsed due to heavy rains that increased the flow of the Ostúa River. The incident was recorded on June 18 and not only caused material damage, but also claimed the life of the former governor of Jutiapa, Armando Palma.

The contract was awarded in July of that same year under a state of emergency due to the emergency generated by the rains, which caused damage in several regions of the country, including the department of Jutiapa. The project faced multiple challenges throughout its execution, including the interruption of work for several months.

In May 2023, the Municipality of Asunción Mita provided an update on the progress of the work, reporting that significant progress had been made in its construction. Finally, this year, the work was completed after local authorities and community representatives submitted a request to the communications portfolio.

Image description for visually impaired people: view of the external structure of the new bridge. (Credit: President Bernardo Arévalo)

Did you know that the famous reality show Is Shark Tank coming to Guatemala? It will be the first country in Central America with its own version and it will definitely be the ideal opportunity for entrepreneurs to present their ideas to potential investors. Find out how to apply and all the related news at:



You may also like

Leave a Comment