The works have been awarded to Trade for an amount of 453,000 euros. According to the calendar of actions established by FGC, the work will begin at the end of this year and will have a completion period of four months. The demand for the new halt is expected to be 23,000 users per year.

The action will consist of the construction of a new platform eighty meters long and three meters wide. In addition, it will have a canopy ten meters long and almost three meters high. The successful bidder will also be in charge of preparing the pedestrian access from Avenida de la Industria, which will connect the Segre industrial estate with the halt and the installation of lighting along its entire length. Likewise, it is planned to create a parking lot.