The proposed facility, located near the coastal town of St Francis Bay, is slated to provide up to 5,200 MW of generation capacity as part of the Integrated Resource Plan (IRP) 2025.
Electricity and Energy Minister Dr. Kgosientsho Ramokgopa delivered the keynote address at the South African Nuclear and Clean Energy Conference, held under the theme “Transitioning from Policy to Execution: Powering a Secure, Sustainable and Industrialised Future.”
Regulators Still Reviewing Thyspunt Plan
While the project is advancing, it remains in the early stages of regulatory scrutiny. Ramokgopa said that the environmental impact assessment and nuclear regulatory processes are being conducted in parallel but have not yet concluded.
A Final Scoping Report was submitted to the Department of Forestry, Fisheries and the Environment on 6 July 2026, allowing the project to proceed to a detailed environmental impact assessment phase. The Minister said that Eskom has yet to choose a reactor vendor or a final reactor design for the proposed site.
The government is utilizing a “technology-neutral Plant Parameter Envelope” for its environmental application. This approach allows officials to assess potential impacts without yet selecting a specific reactor design or vendor.
“The department is preparing a proposed determination for public participation. We will put the case for the additional capacity before the public and consider submissions on their merits,” said Ramokgopa. The National Nuclear Regulator will exercise its independent authority over safety and licensing.
Debate Intensifies over Nuclear Necessity and Tariff Impact
The proposal has drawn sharp debate regarding its necessity and potential impact on electricity tariffs. “The question is, will we need 5 200 megawatts of nuclear by 2040, especially if we take into account what it may cost?” Swilling asked.
The IRP 2025 provides for 5,200 MW of new nuclear capacity. Ramokgopa acknowledged that financing and construction timelines will influence what users ultimately pay, but argued that coal and nuclear can operate alongside one another as the government reviews the coal fleet on its own merits.
Swilling cautioned that previous demand projections had expected growth that did not materialise, Daily Maverick reported. He questioned whether the country will need 5,200 MW of inflexible nuclear capacity by 2040, Daily Maverick reported. A fleet of coastal plants would also require grid upgrades, the same outlet noted.
Skills Gap and Heritage Concerns Flagged for Nuclear Programme
Minister Ramokgopa acknowledged that the lack of recent domestic experience in nuclear construction poses a major risk to the timeline. “One of the biggest inherent risks in this programme is that we have not built a nuclear power plant in the past 50 years or so … at Koeberg, they know how to run an already-built power station. So, the inherent risk is we don’t have people who have built nuclear power stations before,” he said.
The South African Nuclear Energy Corporation (Necsa) welcomed the determination, noting it provides an opportunity to re-establish front-end fuel cycle capabilities.

To mitigate these challenges, the department intends to partner with international firms to build a pipeline of local engineering talent. The government also aims to avoid the planning difficulties that affected the Kusile and Medupi power station projects.
Regarding the Thyspunt location, the South African Heritage Resources Agency has raised concerns, as the area was declared a Grade I Cultural Landscape in January 2025. St Francis Bay, known as “Little Venice,” was developed in the 1950s by Leighton and Ann Hulett, later featuring Southern Africa’s first residential marina.
Minister Prepares Public Case for Nuclear Determination
Electricity and Energy Minister Kgosientsho Ramokgopa said his department is preparing to put the case for an additional 5.2 GW of nuclear capacity before the public and will consider submissions on their merits, World Nuclear News reported.
Ramokgopa emphasised that the consultation would rest on science and evidence rather than ideological bias, Green Building Africa noted. He added that the government had learnt from the Kusile and Medupi build programmes, calling them a template on how not to do things, SAnews reported.
The Nuclear Energy Policy designates Eskom as the owner and operator of nuclear plants and provides for it to retain control under a public-private partnership, the same outlet reported.
As Minister in the Presidency responsible for Electricity from 2023 and Minister of Electricity and Energy from July 2024, Dr. Kgosientsho Ramokgopa holds the statutory authority under Section 34(1) of the Electricity Regulation Act to issue determinations for new generation capacity, including the proposed 5,200 MW Thyspunt nuclear build.
His infrastructure track record includes serving as head of the investment and infrastructure unit in the Presidency from 2019 to 2023 and as Mayor of Tshwane from 2010 to 2016, where he oversaw municipal capital programmes.
A civil engineer by training with a PhD in public affairs, Ramokgopa has acknowledged the execution risk posed by South Africa’s 50-year gap in nuclear construction experience since Koeberg, citing the Kusile and Medupi coal projects as templates on how not to proceed.
Procurement Plan Targets June 2027
Koeberg, currently the only operating nuclear plant in the country, has a nameplate capacity of 1,940 MW and has received 20-year licence extensions. The new Thyspunt project is expected to be much larger. The Minister intends to publish the formal determination under Section 34(1) of the Electricity Regulation Act before June 2027.
Funding options currently being considered include private-sector participation, public-private partnerships, and project finance. “We are going to announce the construction and then separate the engineers from the politics. We will procure nuclear as a backbone for electricity generation in South Africa,” Ramokgopa said.