Road Management Area III Finds Contractor At Fault For Conflicting Speed Signs

Two speed limit signs of 70 km/h and 50 km/h sat just 5 to 10 meters apart on the Vân Phong – Nha Trang expressway, sparking an internal review.

  • Two speed limit signs of 70 km/h and 50 km/h were placed 5 to 10 meters apart at Km1389 on the Vân Phong – Nha Trang expressway.
  • The oversight occurred because a temporary 50 km/h construction sign was left behind after a rest stop connection was completed.
  • Traffic police confirmed that drivers caught exceeding speeds due to the conflicting signage will not face fines.

Drivers expressed concern that the brief distance made it nearly impossible to safely decelerate from 90 km/h without risking sudden braking hazards or penalties.

Inspectors from the Road Management Area III investigated the site at 10:30 a.m. on November 26, 2026. The inspection team included representatives from the Road Management Office III.2, highway patrol officers from Traffic Police Team No. 6 under the Road Traffic Police Patrol and Control Team of Department 6 (Cục Cảnh sát giao thông), and maintenance contractors.

Investigators determined that the 70 km/h sign at Km 1389+260 regulated traffic near the new rest stop, while the 50 km/h sign at Km 1389+250 was a temporary marker meant exclusively for construction zones.

Photo: Báo Xây dựng

Authorities pinned direct responsibility on Công ty TNHH Tân Khánh Hòa KH for failing to remove the temporary restriction after completing the rest stop connection. Crews dismantled the 50 km/h sign on November 26, leaving only the 70 km/h limit in place.

Traffic police assured drivers that no penalties would be levied for speeding violations in that zone. Highway patrol representatives confirmed that the infraction stemmed from faulty infrastructure management rather than driver error.

Following the incident, Road Management Office III.3 initiated a comprehensive review of all highway signs and guidance markers across national routes and regional expressways under its jurisdiction. Maintenance teams were instructed to check for overlapping, redundant, or confusing speed transitions to prevent similar incidents.

Photo: Vietnam+ (VietnamPlus)

The regulatory body overseeing the area, Khu Quản lý đường bộ III, manages five separate expressway routes spanning from Quảng Ngãi to Khánh Hòa.

These connected infrastructure segments include Quảng Ngãi – Hoài Nhơn, Hoài Nhơn – Quy Nhơn, Quy Nhơn – Chí Thạnh, Chí Thạnh – Vân Phong, and Vân Phong – Nha Trang.

During follow-up inspections conducted at 14:00 on November 29, 2026, representatives from Road Management Office III.2, the routine maintenance contractor joint venture, and Công ty TNHH Tân Khánh Hòa KH verified that the temporary hazard markers had been completely cleared. Officials mandated that contractors maintain stringent traffic safety protocols while finishing remaining ancillary structures at the rest stop.

Regional offices were directed to audit sign compliance rigorously, ensuring that all posted limits align accurately with geometric design, surface structure, sightlines, topography, and actual operational requirements.