Scottish Power announced on July 22, a £1.5 billion investment to overhaul the Whitelee Windfarm in Scotland. The project will replace 215 existing turbines with 124 larger models by 2035, effectively doubling the site’s capacity to around 1 gigawatt and providing enough electricity to power approximately 650,000 homes.
Repowering Britain’s Largest Onshore Wind Farm
The Whitelee Windfarm, situated in East Renfrewshire, has been a fixture of the UK’s renewable energy sector since its initial commissioning in 2008. The first phase was officially opened by then-First Minister Alex Salmond in 2009. Originally consisting of 140 turbines, the site has been expanded twice to reach its current size. As the site’s original turbines reach the end of their 20-to-25-year operational lifespan, Scottish Power has unveiled a repowering plan to modernize the facility. The initiative, valued at £1.5 billion ($2.01 billion), aims to transition the site from its current 215-turbine configuration to a more efficient layout featuring 124 significantly taller models.
This transition is designed to maximize the site’s energy output. While the turbine count will decrease—with reports noting the current count of 214 or 215 turbines potentially reducing to 124—the height of the new structures is set to increase. Current turbines measure up to 140 metres at the blade tip, while the new units could reach well above 240 metres. Scottish Power chief executive Keith Anderson emphasized that the scale of these new turbines must be viewed within the context of the landscape, noting that the area was previously utilized for commercial forestry, a lot of which the company has removed to return the environment to more of its natural state.
Operational Strategy and Timeline
The overhaul is scheduled to begin around 2030, with completion targeted for 2035. To maintain continuity in energy production and keep the visitor centre accessible, the company plans to execute the work in three phases. We will repower it in sections over that period of time, and that means we still get the best out of the existing site as we start building the new site,
Anderson explained in an interview. Scottish Power Renewables chief executive Charlie Jordan highlighted the necessity of this work, stating, At this critical moment in the push for home-grown clean, green energy, it's important we don't go in reverse and lose the clean capacity that's been hard-earned over the last two decades as it comes to the end of its operational life.

The project arrives alongside broader discussions regarding the UK’s energy landscape. While Scottish Power recently announced increased half-year earnings of £1.7 billion, CEO Keith Anderson has also addressed the cost of living squeeze. Anderson welcomed the move by Prime Minister Andy Burnham to remove VAT from domestic electricity bills but urged for further action to address household energy debt, which industry group Energy UK predicts could hit £7 billion by the end of the year.
The discourse around wind energy has also included unconventional commentary. Former Downing Street chief of staff Morgan McSweeney recounted a conversation between Prime Minister Keir Starmer and President Donald Trump, in which the President claimed that wind turbines kill birds, which are then eaten by foxes. According to McSweeney, the President suggested that these foxes become too fat to recognise
after eating the birds. Despite such political remarks, Scottish Power maintains that increasing the size and output of the Whitelee site is a brilliant thing
for the country’s renewable energy generation.