Engineering cadres continue their work on the Diyala Olympic Stadium project, under the direct supervision of the Ministry of Youth and Sports.
A statement by the Ministry of Youth and Sports, followed by the (INA), today, Wednesday, stated that “The Director General of the Engineering Department, Abdul Khaleq Khader Al-Khafaji, followed in the field the progress of work on the Diyala Olympic Stadium project, which can accommodate 30,000 spectators, to review the stages of work and in the presence of the Resident Engineer Department and the company.” “executed.”
The statement continued, “The work reached the stage of hammering piles under the foundations of the stadium, and more than 450 piles were hammered at a depth of 12 meters out of 770 piles. In addition, a meeting was held in the presence of the implementing company, to discuss the work progress program, and to address deviations in the program by intensifying efforts and increasing… Project working hours.