Belgian authorities ordered Google to halt construction on a data center project in Aiseau-Presles on Friday following an unpermitted expansion.

The intervention comes after Greenpeace alerted regional officials that building work advanced significantly during November despite the revocation of a key modification permit.

The dispute centers on a facility located in a business park across a former mining site in the Charleroi region. An initial 2024 building permit remains valid. Regional authorities said Google improperly constructed a three-hectare building under a modified plan that was officially rejected earlier in the year.

  • Regional officials issued a formal work stoppage order on November 26, 2026, after controllers inspected the site.
  • The rejected expansion sought to increase facility power from 160 megawatts to 240 megawatts and use water from the Sambre river for cooling.
  • An infraction report will be transmitted to the Charleroi prosecutor’s office during the week of November 30, 2026.

Minister Refuses Permit Modification for Data Center

The conflict originated when Google requested modifications to its original 2024 authorization. The company sought to combine two planned data centers into a single larger unit and switch from an air-cooling system to drawing cooling water directly from the Sambre river.

In August, regional minister François Desquesnes refused the permit modification following citizen appeals and opposition from groups such as the Stop Data Center collective. Officials argued that river withdrawals could not be guaranteed during recurring drought conditions.

“They built the new building as if they had it, whereas they didn’t have it (this amended permit),” Nicolas Yernaux said, according to L’essentiel.

Yernaux said inspectors observed a major infraction on site. He confirmed that an infraction report would be sent to the prosecutor.

Photo: Le Soir

Regional Impact and Environmental Demands

The controversy spans an expansive fifty-hectare former mining zone situated across the municipalities of Farciennes, Sambreville, and Aiseau-Presles. A completed first facility is situated in Farciennes. Municipal leaders clarified that the disputed ongoing construction sits within the borders of Aiseau-Presles.

Environmental campaigners raised concerns regarding the massive electricity and water demands of such tech installations. They pointed to an existing data center in Saint-Ghislain that consumed 2.7 billion liters of water in 2025.

Nadia Cornejo, serving as spokesperson for Greenpeace Belgium, cautioned that the climate crisis will only intensify within local regions. She asserted that the deployment of such energy-intensive mega-installations warrants public debate rather than quiet administrative agreements.

Raphaël Stokis said that the substantial power increase requested by the tech giant creates questions about grid capacity for other businesses seeking regional installation. Local investors already struggle with connection responses from network operators like ORES or Elia.

Photo: RTL Info

Administration Prepares Infraction Dossier for Prosecutor

Controllers from the Walloon administration documented that while pumping pipelines had not yet been installed, structural elements tied to the ministerial refusal had indeed been erected, according to DHnet. Raphaël Stokis explained that regional services prepared an official record matching the 2024 permits, the denied changes, and the actual structures built on site.

The resulting infraction dossier is scheduled for transmission to the public prosecutor during the week of November 30. This leaves the judiciary to determine whether formal criminal proceedings will follow, as RTBF reported.

The multinational firm lodged a cancellation appeal with the Council of State on October 17 against the ministerial decision. Greenpeace and local residents filed an intervention request on November 16 to defend the revocation.

Controllers Visit Site While Workers Remain Employed

Following a prompt from Greenpeace, which tracked progress using drone imagery, controllers commissioned by the Walloon region visited the active site where approximately 300 workers were employed, as noted by DHnet and La Libre.be.

Google maintains that ongoing work on the site was intended to ensure site security and preservation while legal challenges remain pending. The multinational corporation previously filed an appeal with the Council of State against the ministerial revocation.

Photo: L'essentiel

“We are committed to maintaining an open and collaborative dialogue with the regional government and experts regarding our investments in Wallonia,” the company said in a separate statement reported by RTL Info and 7Sur7.

According to the news, François Desquesnes serves as the Wallonia infrastructure minister. In August, acting in that ministerial role, he refused and revoked Google’s requested permit modification to merge planned facilities and alter the cooling system due to drought concerns.

A public hearing regarding the corporate appeal before the Council of State is scheduled for January 7, 2027.